Wisconsin DNR's SFY2026 Clean Water Fund Program and Safe Drinking Water Loan Program funding lists, adopted April 2026, show 1,091 projects, down from 1,163 in the prior cycle. The tracked value across the current list stands at $2.6B. During this period, 430 projects appeared on the priority list for the first time, worth $1.4B, while 175 entered the fundable range, representing $639.2M. Another 480 no longer appear on the current list, though the list does not say why. Cost changes hit 332 projects, with 239 rising and 93 falling, for a net change of +$297.8M on file.
Construct New WWTP. Est. cost $126.5M.
Upgrade WWTP - Phosphorus, Upgrade Equip, Add Biosolids Drying. Requested $55.5M.
Construct New CL contact tank/UV disinfect/pumps. Requested $52.3M.
The clearest movement this cycle belongs to City of Portage, where a wastewater treatment upgrade covering phosphorus removal, equipment upgrades, and biosolids drying carries a requested amount of $55.5M on file. Two new entries also stand out: City of Jefferson appeared on the priority list for the first time with a wastewater treatment plant construction project estimated at $126.5M, and City of Oak Creek was added to the list with a drinking water project, including a CL contact tank, UV disinfection, and lift pumps, estimated at $50.0M. On a smaller scale, City of Stanley and Village of Iron Ridge both climbed in priority rank, for well rehabilitation estimated at $326K and headworks upgrades estimated at $1.5M, respectively.
Across the category rollup, wastewater treatment carries the largest tracked value at $2.0B across 223 projects, while collection and sewer work spans the most projects of any category, 307, totaling $922.3M. Watermain and distribution work follows closely in project count at 226, valued at $385.7M, and PFAS and emerging contaminants projects, while fewest in count at 38, still represent $385.8M, a signal that smaller categories can carry outsized dollar weight relative to their project counts.
The net shrinkage of 72 projects on the list sits apart from the separate counts of additions and removals, since new listings, entries into the fundable range, and no-longer-listed projects are drawn from different parts of the roster and do not reconcile into that single figure. What is concrete is this: $639.2M in projects moved onto the intended use plan roster, and $297.8M in net cost changes shows that estimates on file continue to move upward more often than down. Readers tracking Clean Water Fund Program and Safe Drinking Water Loan Program entries will want to watch which of the 175 fundable-range projects advance onto the IUP roster in the next cycle.
Projects the state has flagged as fundable — the closest signal to imminent procurement. Ordered by requested amount.
| Entity | Scope | Program | Requested |
|---|---|---|---|
| City of Portage | Upgrade WWTP - Phosphorus, Upgrade Equip, Add Biosolids Drying | CWFP | $55.5M |
| City of Oak Creek | Construct New CL contact tank/UV disinfect/pumps | SDWLP | $52.3M |
| City of Oshkosh | Upgrade WWTP - Construct Tertiary Filtration for Phosphorus | CWFP | $44.3M |
| City of Horicon | Upgrade WWTF | CWFP | $39.8M |
| City of Sheboygan | Southside Sanitary Interceptor Sewer System - Phases 1 & 2 | CWFP | $31.7M |
| Milwaukee MSD | Install Oklahoma Avenue MIS Capacity Improvements C03013C01 | CWFP | $27.6M |
| City of Sparta | Upgrade WWTP for Phosphorus Compliance | CWFP | $14.5M |
| Green Bay MSD | Upgrade East River Lift Station & Force Main | CWFP | $14.4M |
Projects that climbed materially in priority (rank, or priority score where a state scores projects) since the previous list — the least-watched signal in the document.
| Entity | Scope | Program | Rank movement |
|---|---|---|---|
| City of Stanley | Rehab Well #3 | SDWLP | score 174 → 388 |
| Village of Iron Ridge | Upgrade Headworks - Replace Pumps; Install New Screen | CWFP | score 50 → 84 |
| Village of Superior | Relocate Outfall Piping for WWTP | CWFP | score 66 → 99 |
| City of Mayville | Replace Watermains on Muzzy St and Allen St | SDWLP | score 54 → 77 |
| Lakeland SD #1 ‐ Oneida | Upgrade WWTP | CWFP | score 62 → 84 |
| Village of Bagley | Replace SS - Jackley Lane, Walnut & Chicago Street | CWFP | score 50 → 65 |
| Dunn SD | Rehab Sanitary Sewer and Upgrade Lift Stations | CWFP | score 50 → 65 |
| Brockway SD | Replace Force Main - Lincoln Street | CWFP | score 54.9 → 69.6 |
| Iron River SD | Stabilize and Upgrade Lift Station | CWFP | score 75 → 85 |
Projects seeking SRF financing — not every municipal water or wastewater project in Wisconsin. Source: Wisconsin DNR — Clean Water Fund Program, Safe Drinking Water Loan Program (IUP/PPL). Stages are labeled precisely; "no longer listed" does not assert an outcome.